The most common dependency relationship is a finish-to-start relationship. Task P (predecessor) must be finished before task S (successor) can start. The least ...
UnderstandingTaskDependenciesinProjectManagement
Dependenciesaretherelationshipsamongtaskswhichdeterminetheorderinwhichactivitiesneedtobeperformed.Therearefour(4)typesofdependencyrelationships.
Typesofdependencies
FinishtoStart
PredecessormustfinishbeforeSuccessorcanstart.[Landmustbepurchasedbeforeroadbuildingcanstart]
StarttoStart
PredecessormuststartbeforeSuccessorcanstart.[RoadexcavatingmuststartbeforeAsphaltcanbelaid]
FinishtoFinish
PredecessormustfinishbeforeSuccessorcanfinish.[LayingAsphaltmustbecompletebeforelinepaintingcanbecompleted]
StarttoFinish
PredecessormuststartbeforeSuccessorcanfinish.[Roadexcavatingmuststartbeforelinepaintingcanbecompleted]
Dependenciesaretherelationshipsoftheprecedingtaskstothesucceedingtasks.Tasksmayhavemultipleprecedingtasksandmultiplesucceedingtasks.Themostcommondependencyrelationshipisafinish-to-startrelationship.TaskP(predecessor)mustbefinishedbeforetaskS(successor)canstart.Theleastcommonrelationshipisthestart-to-finishrelationship.ProjectInsight,projectmanagementsoftware,supportsallfourdependencyrelationships.
ProductDevelopmentActivityList
ThechartaboveshowshowaProductDevelopmentActivityListmaylookaftertheprojectteamdeterminesthetaskrelationships.Inourexample,onlyfinish-to-startrelationshipswereused.
Itisalwayseasiertoarrangealltasksintermsofafinish-to-startrelationshipandan'assoonaspossible'constraint.Thisdependencytypeistheeasiestrelationshipforotherstounderstandandwillusuallyresultinalongerthannormalschedule.Thisgivestheschedulemore'slack.'Youmaythenutilizetheotherrelationshipsaswaystoshrinkthedurationoftheoverallschedule.Ifyouusefinish-to-startandassoonaspossible,youwillbeabletochangethescheduleinProjectInsight,projectmanagementsoftware,withjustacoupleofmouseclicks.
<
延伸文章資訊
- 1Setting Task Predecessors - Tax Reporting - Oracle Help Center
The Predecessors tab enables you to set predecessors for the current task. For template tasks, yo...
- 2Link tasks in a project - Microsoft Support
- 3Overview of task predecessors | Adobe Workfront
Whether the predecessor and successor tasks belong to the same project or to two different projec...
- 4Gantt Chart Dependencies - Mavenlink Knowledge Base
- 5Add Predecessors to Each Task | Microsoft Project ... - GoSkills
To link tasks together, the best approach is to insert the predecessor column into the Gantt char...