The practical calculation of schedule variance | PMI
文章推薦指數: 80 %
The cost performance index (CPI) is a measure of the conformance of the actual work completed (measured by its earned value) to the actual cost incurred: CPI = ... Learning Library Thepracticalcalculationofschedulevarianceintermsofschedule Tweet ConferencePaper Scheduling,CostManagement 19October2008 Warburton,RogerDavidHand|Kanabar,Vijay Howtocitethisarticle: Warburton,R.D.H.&Kanabar,V.(2008).Thepracticalcalculationofschedulevarianceintermsofschedule.PaperpresentedatPMI®GlobalCongress2008—NorthAmerica,Denver,CO.NewtownSquare,PA:ProjectManagementInstitute. Abstract Thevariationinaproject'sactualschedule,ascomparedtoitsplannedschedule,ismeasuredbyitsschedulevariance(SV),whichmeasuresthedifferencebetweentheearnedvalue(EV)(thevalueofworkactuallyperformed)andtheplannedvalue(PV),soSV=EV–PV.However,SVisexpressedasamonetaryunit(e.g.,indollars),whichmakesitdifficulttounderstandasavarianceintheschedule,whichshouldpresumablybemeasuredintimeunits,suchasdaysormonths.Severalauthorshaveproposeda“time-based”earnedschedule(ES),whichiseasiertointerpret. Unfortunately,therearenogenerallyavailableformulasforcalculatingES,whichmeansthatitisdifficulttocalculate.WeremedythisshortcomingbypresentingformulastocalculateES.Theformulasarerelativelystraightforward,andareillustratedbyapplicationsintwoindustries:constructionandsoftwaredevelopment.Theresultsandconclusionsfromthetwoindustriesarequitesimilar,andindicatethataslongasprojectlaborcurvesfollowthegeneral“S”shape,theformulasshouldhavewideapplicability. Thefirstusefulresultisthattheformulasshowhowthecostandschedulevariancesevolveovertime.Thatis,theydemonstratehowESperformsoverthelifeofaproject,andexplainitsbehavior.TheyalsoallowthecalculationofActualCosts,PlannedValue,andEarnedValueovertime.Therefore,onecanalsoeasilycalculatethecostperformanceindex,CPI(t),andscheduleperformanceindex,SPI(t),bothofwhicharealsofunctionsoftime. Theabilitytomakescheduleforecastswithoutperformingacompletebottom-upanalysishasbeenlongdesiredbyprojectmanagers.Thatdeficiencyiseliminated:projectmanagerscandevelopearlyscheduleestimates,andthentracktheschedule'sactualperformanceastheprojectevolves.Whilemuchworkremainstobedone,itappearsthattheformulasareausefulstartingpointandshowgreatpromise. Introduction Anbari(2003)describedthemajoraspectsoftheearnedvaluemethod(EVM),includingsomeextensionsnotfoundinthesimplifiedguidetoEVMterminologyprovidedinAGuidetotheProjectManagementBodyofKnowledge(PMBOK®Guide)(ProjectManagementInstitute,2000).EVMusescost,orsomeotherreasonablesubstitute,asthecommonmeasureofprojectperformanceforbothcostandscheduleparameters,andhaswideapplicabilitytobothpublicandprivatesectorprojects.Ontheotherhand,non-usersofEVMoftenindicatethatthemethodishardtouse(Fleming&Koppelman,2000;Kirn,2000). Thekeyconceptistheearnedvalue,EV,whichconvertsprojectaccomplishmentsfromphysicalunitsofmeasure(e.g.,milesofroadwayordeliverablescompleted)tofinancialunits(e.g.,dollarsorlaborhours).EVMalsodefinestheplannedvalue(PV,thetime-phasedbudgetbaseline)andtheactualcost(AC,thecumulativecostspenttoagivenpointintimetoaccomplishanactivity,workpackage,orproject).ACisdeterminedasthecosttoearntherelatedvalue. FromEVtoTV Aproject'scostperformanceismeasuredbycomparingEVtoAC,whilescheduleperformanceismeasuredbycomparingEVtoPV.Theschedulevariance,SV,isameasureoftheconformanceoftheactualprogresstotheplannedprogress:SV=EV–PV.AmajorcriticismofthestandardEVMisthattheschedulevarianceismeasuredincostunits,nottime.Thisissuehasbeenaddressedintwoways: ConvertingtheSVintotimeunits(Anbari,2003) Measuringthetimedelayonthecumulativecostcurve(Fleming&Koppelman,2000) ThefirstoftheaboveapproachesinvolvesdefiningtheaverageACpertimeperiod,calledthespendrate(ACRate),andtheaveragePVpertimeperiod,calledtheplannedvaluerate(PVRate).PVrateisdefinedasthebaselinebudgetatcompletion(BAC)dividedbythebaselinescheduleatcompletion(SAC).Thus,PVRate=BAC/SAC.TheusefulnessofPVRateisthatittranslatesSVintotimeunits.DividingSVbyPVRateconvertsSVintotimeunits,whichisreferredtoasTV,whereTV=SV/PVRate(Anbari,2003). Inthesecondapproach,TVismeasuredgraphicallybydrawingahorizontallinefromtheintersectionoftheEVcurvewiththestatusdatetothePVcurveandreadingthedistanceonthehorizontaltimeaxis(Fleming&Koppelman,2000).Bothoftheaboveapproacheshavethedesirableresultofdefiningtheschedulevarianceintimeunits,whichisamoreusefulcharacteristicofascheduleover-run. However,bothoftheaboveapproachessufferfromaseriousdrawback.Bothassumethatalloftheparametersareindependentoftime.Forexample,thePVRateiscalculatedasthetotalbudgetdividedbythetotalschedule(bothatcompletion),andisassumedtobeconstantoverthelifeoftheproject.WhenonedividesthecurrentSV(attime,t)bythePVRate,oneisassumingthattheaveragePVRateappliesforalltime. Theassumptionthattheparametersareindependentoftimeismanifestlynottrue.ThiscaneasilybeseenbyexaminingthebehaviorofSVattheendoftheproject.Asalloftheactivitiesarecompleted,thentheearnedvalueapproachestheplannedvalue.Moreprecisely,EV→PV,andSV=EV–PV→0.SVis,therefore,inherentlyafunctionoftime,andtoemphasizethefactwewilldenoteitasSV(t).Infact,itiseasytoseethatallquantitiesinEVMarefunctionsoftime. Acceptingthattheparametersarefunctionsoftimepresentsadilemma:Attheendoftheproject,thescheduleover-runisadefinitenumber,suchas6weeks,andismanifestlyaconstant.(Ofcourse,theschedulemayunder-run,butforsimplicitywewillrefertoanover-run.)Howdoweestimatetheconstant,eventual,finalscheduleover-runfromquantitiesthatvaryovertime?Anevenmoreintriguingquestionis,Canweestimatetheconstantvalueforthefinalscheduleover-runearlyintheproject?Thatis,givensomedataonCVandSV,canwepredicttheeventualfinalscheduleover-run?Finally,canweestimatetheover-runintimeunits? Forascheduleover-runpredictiontobereasonable,oneshouldexpectthatitsestimationremainconstantoverthelifeoftheproject.ThissuggeststhatTVshouldbeaconstant.Inwhichcase,PVRateshouldbeafunctionoftime,asindicatedinequation(1): KnowingthatSV(t)isinherentlyafunctionoftime,thenforTVtobeaconstant,PVRatemustalsobeafunctionoftime.Ifso,thenhowdoesonecalculatePVRate(t)?Ananalogousargumentshowsthatthecostvariancemustalsobeafunctionoftime,CV(t). Inthispaper,wewillmakesomeprogressinansweringthesequestionsbydevelopingamodelthatpredictsthebehavioroftheEVMparametersovertime.Thiscanevenbedoneearlyonintheproject'slife.Whatemergesisapredictionfortheeventualscheduleover-runfortheentireproject,andintimeunits. CPIandSPI Thecostperformanceindex(CPI)isameasureoftheconformanceoftheactualworkcompleted(measuredbyitsearnedvalue)totheactualcostincurred:CPI=EV/AC.Thescheduleperformanceindex(SPI)isameasureoftheconformanceofactualprogress(earnedvalue)totheplannedprogress:SPI=EV/PV.Inbothoftheaboveformulas,avalueof1.0indicatesthattheprojectperformanceisontarget.WhenCPIorSPIaregreaterthan1.0,thisindicatesbetter-than-plannedprojectperformance,whileCPIorSPIlessthan1.0indicatespoorer-than-plannedprojectperformance.TheformulasusedtocalculatetheCPIandSPIindicesaregenerallybasedoncumulativecosts. Theinverseoftheaboveformulasareusedinforecasting(Anbari,1980;Egan,1982;Cioffi,2002;Webster,2002).DividingtheforecastedbudgetbythecurrentCPIgivesapredictionofthefinalbudgetifperformancecontinuesatthesamerate.AsimilarcomputationcanbeperformedusingtheSPI. However,justastheschedulevarianceisafunctionoftime,SV(t),byanalogousreasoning,thescheduleperformanceindexmustbeafunctionoftimealso,SPI(t).Andofcourse,thisalsomeansthatthecostperformanceindexmustbeafunctionoftimeaswell,CPI(t). Graphsofthevariancesandperformanceindicesovertimeprovidevaluableinformationabouttrendsinprojectperformance.Whencorrectiveactionsareimplemented,thechangesinthebehavioroftheindexesrevealtheimpactofthechanges.Suchgraphscanbeveryeffectiveinprojectreviews.However,examiningandanalyzingthechangesintheparametersbegsthequestionofhowtheychangeovertime.Forexample,“WhatisthebaselinechangeinCPIovertime,andhowdoesitcomparetothemeasuredperformance?” CostandScheduleForecasting Theestimatedcosttocompletetheremainderoftheactivitiesforaprojectiscalledtheestimatetocomplete(ETC),whiletheestimateofthefinalcostatcompletioniscalledtheestimateatcompletion(EAC).MethodsforcalculatingEACdependontheassumptionsmadeaboutthefutureperformanceoftheprojectversusthehistorical,establishedperformancetodate.ThePMBOK®Guideprovidesthreeapproaches,basedonthreedifferentsetsofassumptions: Whentheassumptionsunderlyingtheoriginalestimateareflawed Whenpastperformanceisnotagoodpredictoroffutureperformance Whenpastperformanceisagoodpredictoroffutureperformance ManyformulashavebeenproposedtocalculatetheEAC,andunderavarietyofassumptions(Anbari,2003;Fleming&Koppelman,2000;Kerzner,2006).However,accordingtoAnbari(2003),“EVMhasnotbeenwidelyusedtoestimatethetotaltimeatcompletion,totalprojectduration,orschedule…basedonactualperformanceuptoagivenpointintheproject.”Usingreasonableassumptions,Anbariprovidedformulasfortheproject'stimeestimateatcompletion(TEAC)andtimevarianceatcompletion(TVAC),basedonthebaselinescheduleatcompletion(SAC)andtheactualperformanceuptoagivenpointintheproject(Anbari,2001,2002). ThedifficultywithalloftheaboveformulasisthattheyassumethatthevaluesforCPIandSPIareconstant.Evenifoneassumesthatthecurrentprojectperformanceisanexcellentpredictoroffutureperformance(assumption#3),onestillneedstoassumethat:1)thecurrentvaluesofCPIandSPIareconstant;and2)thattheyarerepresentativemeasuresoftheentirefutureperformanceoftheproject.WhengraphsofCPIandSPIarechangingovertime,whichistheusualcase,thecriticalquestionbecomes“HowdoCPIandSPIevolveovertime?” ThisimportanceofthisquestioncanbeseenbyreviewingthebehavioroftheSPI.AsnotedbyFlemingandKoppelman(2000)andKerzner(2006),attheendoftheproject,theSPIalwaysapproaches1.0.Thisisthesimpleresultofthecompletionofallproposeddeliverables;thatis,aseachactivitycompletes,theearnedvaluebecomesequaltotheplannedvalue.Thisistrueeveniftheprojectislate,inwhichcasetheSPIstillapproaches1.0,butaftertheplannedcompletiondate.WewouldliketoknowhowlatetheprojectisgoingtobebydecodingthebehaviorofSPI(t)overtime. ConstructionLaborCurves Wenowturntoanalyzinglaborcurvesthataretypicallyappliedintheconstructionindustry.Wideman(1994,2001,2004)providedlaborcurvesforaprofitablecivilcontractwhichwaspredominantlyformworkandconcreteplacing.ThedataisredrawninExhibit1,whichshowsahistogramoftheproductionworkforceoverthe38-weekprojectduration.Thereisaninitialperiodofbuild-up,aperiodofpeakloading,followedbyaperiodofprogressivedemobilizing. Exhibit1–Actual(Histogram)andModel(Trapezoidal)LaborCurvesforaConstructionProject Allen(1979)suggestedthatasimpletrapezoidalfigurecanbeusedasanexcellentapproximationtotheactuallaborloading.Thetrapezoidalprofile,whichisalsoshowninExhibit1,consistsofalinearramp-uptoapeakafter50%oftheschedule,aconstantpeakloadendingafter75%oftheschedule,andaramp-downtotheend.InExhibit1,theagreementbetweentheactualprojectdataandtheapproximateloadingisquitestriking.Infact,theestimateofthetotallaborfromthetrapezoidalcurveiswithin2%oftheactualvalue. Warburton(2008)developedamodelusingtheequationsforthetrapezoidalcurve,whichisdenotedasc(t).Thepeakvalueofthelaborcurveis,P,andtheprojectendsattime,Te.Theramp-upspanstheinterval[0,Te/2].UsingAllen'srule#5,(thepeaklaborloadingoccursfrom50%to75%oftheproject),theconstantsectionspanstheinterval[Te/2,3Te/4].Thus,theequationforthetrapezoidalcurveis(Warburton,2008): PlannedValue Theinstantaneousrateatwhichactivitiesareplannedtobecompletedisdefinedastheinstantaneousplannedvalue,PVI(t).Asactivitiesarestaffed,thereisnoguaranteethattheyarecompletedontime,andsoequation(3)representstheplannedcompletionofactivities.Therefore,thecurveforPVI(t)followsthesamecurveastheinstantaneouslaborrate,c(t).Traditionally,thePlannedValue,PV(t),isdefinedasthecumulativesumoftheprevious,instantaneousPVI(t),andsoisdefinedas: TheinstantaneousandcumulativeplannedvaluesareplottedinExhibit2(thedottedlines).Thetraditionalcumulativeversion(Exhibit2b)showsthetypical“S”curveassociatedwithcumulativecosts.AccordingtoinvestigationsbySinghandLakanathan(1992),theapplicationof“Scurves”forcashflowprojectionscanachieveaccuraciesofapproximately88–97%,andtheshapeoftheS-curvebudgetversustimeisaquickwaytojudgeperformance.Thisispreciselytheobjectiveofmacroestimationmethods:anearlyestimationofprojectperformancefromoverallsystemparameters. Exhibit2–PlannedValue(dottedline)andActualCost(solidline)forTrapezoidalLaborCurvea)InstantaneousLabor b)CumulativeLabor TheWarburtonmodelassumesthatastheprojectproceedsnotallactivitieswillbecompletedontime,andoneassumesthatafractionoftheactivitiesthataresupposedtobecompletedattime,t,arerejectedforsomereasonandrequireextrawork.Projectmanagersshouldbeabletoestimatethisparameterearlyonintheprojectastheinitialactivitiesarecompletedandanyover-runsnoted.Softwareprojectdatasuggeststhaterrorratesremainconstantoverthelifeofaproject,sotheavailabilityofanearlyestimateoftherejectionrateisareasonableassumption. Thecompletionofrejectedactivitieswillbedelayed,anditisassumedthatthisdelayisaconstantamount,τ.Thatis,eachactivitythatisrejectedisdelayedthesameamount.Unliketherejectionrate,thereislittledataontheaveragedelayexperiencedbyindividualactivities.Therefore,thereasonablenessofthisassumptionneedstobeevaluatedbycomparingrealprojectdatawiththemodel. ActualCost TheinstantaneousActualCost,ACI(t),includestheworkperformedonboththeactivitiesthatweresuccessfullycompletedandthosethatwererejected.Attime,t,theactivitiesthatwererejectedattimet–τwillbesuccessfullycompleted.Therefore,theinstantaneousActualCostattime,t,is: Theparameter,α,representstheaverageproductoftherejectionrateandtheworkrequiredtofixtheproblem.Weseefromequation(5)thatαisthefractionalextraworkrequiredforeachplannedactivity.Usingthismodel,WarburtoncalculatesthecumulativeActualCost,AC(t),byintegrating,exactlyasinequation(4).ThecumulativeActualCostasafunctionoftimeisshowninExhibit2(solidline).TheActualCostincreasesasthecostoftherejectedactivitiesaccumulates.TheActualCostast→∞representsthetotalcostoftheproject,whichis(Warburton,2008): Thisisreasonable,becauseitsaysthatwhenthecostover-runineachactivityisonaverageafixedpercentage,theendresultisacostover-runfortheentireprojectbythesamepercentage.Itisinterestingtonotethatinthismodel,thetotalprojectcostdoesnotdependonthetimedelay,τ,butonlyonthefractionofactivitiesthatwererejected. EarnedValue TheEarnedValueisthevalue,orcost,ofthesuccessfullycompletedactivities.Ineachinterval,afraction,α,oftheactivitieswererejected,sotheremainingactivities(1–α)werecompletedandearnvalue.Also,previouslyrejectedactivitiesthatarecompletedinthisintervalalsoearnvalue.Therefore,theinstantaneousEarnedValueis: Exhibit3ashowstheinstantaneousEarnedValue(solidline)asafunctionoftimeascomparedtothePlannedValue(dottedline).TheEVisinitiallydelayedrelativetotheplannedvalue,buteventuallycatchesup.Theearnedvalueisslightlydelayedattheend,representingascheduleover-run. Exhibit3–PlannedValue(dotted)andEarnedValue(solid)forTrapezoidalLaborCurve a)Instantaneous b)Cumulative ThecumulativeEarnedValue(EV)isfoundbythesameprocessasforthecumulativeActualCost—integrating.Exhibit3bshowsthecumulativeEarnedValueasafunctionoftime(solidline)ascomparedtothecumulativePlannedValue(dottedline).Bothcurvesapproachthesamevalueast→∞becausethetotalnumberofactivitiesintheprojectremainsthesame.Theearnedvalueisdelayedbecausesomeoftheactivitieswererejectedandcreditfortheirworkwasonlyearnedwhentheywerefinallycompletedafterthedelaytime. Ifextraactivitieshadbeenadded(scopecreepoccurred),thentheearnedvaluewouldapproachahigherlevelthantheplannedvalue.Sincethenumberofactivitieshasnotchanged,thetotalearnedvaluemustbethesameasthetotalplannedvalue.ThisisconfirmedintheWarburtonmodelbythefollowingrelations,whichshowthePlannedandEarnedValuesast→∞: CPI(t)andSPI(t) TheCostPerformanceIndex(CPI)isdefinedastheratioofEarnedValuetoActualCost,whiletheSchedulePerformanceIndex(SPI)isdefinedastheratioofcumulativeEarnedValuetocumulativePlannedValue(PMI,2000).BothCPIandSPIaretraditionallydefinedintermsofthecumulativevalues.However,fromequations(3)–(5),onecanimmediatelyseethatthesequantitiesareafunctionoftime,andso: ThebehaviorofCPI(t)andSPI(t)areshowninExhibit4.Theperformanceovertimeofthetwoindexesisdifferentandquiteinteresting.CPI(t)immediatelyfallsto1–αbecauseinthefirsttimeinterval,someactivitiesarerejected.Astherejectedactivitiesarecompletedaftertime,t=τ,creditisearned,andtheCPIrisesslightly,butitremainslowovertheentirelifeoftheproject.Attheendoftheproject,CPI(t)doesnotapproach1.0,itapproachesthevalueshowninequation(10),whichdependsdirectlyontherejectionrate. Exhibit4–CumulativeCPI(t)andSPI(t)asFunctionsofTime However,thebehaviorofSPI(t)isquitedifferent.Italsofallsimmediatelyto1–α,butiteventuallyclimbsbackto1.0attheendoftheproject,asitshould.However,SPI(t)reachesthevalue1.0aftertheprojectedscheduledcompletion.Theactualvaluesattheendoftheprojectare: AcriticismoftheuseofSPIisthatsinceitapproaches1.0attheendoftheproject,itisnotusefuloverthelastthirdoftheproject(Corovic,2007;Fleming&Koppelman,2003;Lipke,2003,2004;Henderson2004;Vandevoorde&Vanhoucke,2006).However,Exhibit4showspreciselyhowandwhenSPI(t)approaches1.0.Knowingtheprecisetime-dependentbehaviorofSPI(t)somewhatbluntsthiscriticism,becausewiththeabovemodelonecancomparetheactualperformanceofSPI(t)totheprojectedperformance.ThecriticismthatthevalueofSPI(t)isinmonetaryunitsisstillvalid,andwewilladdressthislater. SoftwareLaborCurves Putnam(1978)pioneeredtheuseoftheNorden-Rayleighcurvetodescribethenumberofpeopleworkingoncomplexsoftwareprojects.ThePutnam-Norden-Rayleighcurve,nowknownasPNR,appearstoapplytomanytypesofsoftwareprojects,particularlyembeddedsoftwaresystems(Warburton,1983).Thenumberofpeopleworkingonaprojectasafunctionoftime,m(t),isgivenby: Tisaconstantthatdenotesthetimeatwhichthenumberofpeopleisatthemaximum—thelaborpeak.Kisaconstantthatcanbedeterminedbytheconditionthatthetotalcostoftheproject,i.e.,thetotalnumberofman-yearsis,N.AcomparisonofthePNRandtrapezoidallaborcurvesisshowninExhibit5.TheinstantaneouslaborratesareshowninExhibit5a,whilethecumulativevaluesareshowninExhibit5b,bothofwhichshowthetypical“S”shape.TheWarburton(2008)modelcanbeappliedtothePNRcurveexactlyaswasdoneforthetrapezoidallaborcurve.Theplannedvalue,actualcostandearnedvaluearecomputedusingintegralsasbefore,justreplacingthec(t)ofthetrapezoidalcurvewithm(t)fromequation(11). Exhibit5–ComparisonofTrapezoidalandPNRLaborCurvesa)InstantaneousValues b)CumulativeValues Exhibit6comparesthecurvesthatresultforCPI(t)andSPI(t)fromthetwomodels.Theparametershavebeenselectedsothatbothmodelshavethesametotalcostandthesamelaborpeak.Despitetheapparentlyquitedifferentlaborcurves,thebehaviorofCPI(t)andCPI(t)overtimeisremarkablysimilarinthetwocases—seeExhibit6. Exhibit6–ComparisonofCPI(t)andSPI(t)forTrapezoidalandPNRLaborCurvesa)TrapezoidalLabor b)PNRLabor ChristianandKallouris(1991)establishedthatformostprojectsthetypicalcumulativelaborprofileisan“S”curve.ThissuggestsanintriguingandpotentiallysignificantpropertyoftheWarburtonmodel: ThebehavioroftheCPI(t)andSPI(t)curvesovertimeformostprojectsshouldbesimilartothoseshowninExhibit6. Therefore,aslongasaproject'slaborcurveistheusual“S”shape,theconclusionisthattheshapeoftheCPI(t)andSPI(t)curveswillfollowthatshowninExhibit6. EarlyEstimationofCostandScheduleOver-runs Wenowturntoestimatingintheearlystagesofaproject,thefinalvaluesoftheproject'scostandscheduleover-runs.Intheearlystagesofaproject,thelaborcurveislinear,andgivenbythefirstpartofequation(3).Inthisregion,theplannedvalue,actualcost,andearnedvalueareeasilycomputed,andareallfunctionsoftime: CalculationoftheCostVariance,CV(t) UsingthestandarddefinitionofCV(t),wehavefromequation(14)and(13): Rearrangingequation(15)givesthevalueforthecostover-runparameter,α,whichisaconstant: Tocalculateα,weneedthevaluesforPandTe.ThisratiocanbefoundbynotingthattheslopeofthePlannedValuelaborcurveis2P/Te.Therefore,intheearlystagesofaprojectwecanestimatetheslopeoftheplannedvaluecurve,whichwedenoteasSPVinequation(16).Sowecancalculateαfromthetimedependentcostvariance,CV(t),accordingtoequation(16).Noticethatthedelayparameter,τ,doesnotoccurhere,andsowecanuseequation(16)tocalculateα.Weemphasizethatαisaconstant,andisaglobalpropertyoftheentireproject. CalculationoftheScheduleVariance,SV(t) UsingthestandarddefinitionofSV(t),wehavefromequations(14)and(12): Forconvenience,wehavedefinedtheconstant,Q,whichdependsonα,whichweknowfromequation(16).Thequadraticinequation(18)hasastraightforwardsolution: Therefore,wecancalculatethescheduleover-run,τ,fromSV(t).Weemphasizeagainthatτisaconstant,andisthepredictionofthetotalscheduledelayfortheproject;thatis,itisaglobalpropertyoftheentireprojectanddoesnotdependontime. Intherealworld,therewillofcoursebenoiseinthedata.However,ifwecanobtainreasonablevaluesforCVI(t)andSV(t),thenwecanestimatevaluesforαandτ.Thenwecanestimatethecostandscheduleover-runsfortheproject.Bothoftheseestimateswillremainconstantovertime,andsoaregenuinelyusefulpredictionsofthecostandscheduleover-runs.Further,thescheduleover-runparameterisintimeunits. AnExampleoftheEstimationofCPI(t)andSPI(t) Wenowshowhowthemodelisusedinpractice.Intheearlystagesofaproject,theplannedvaluecurveisknown.Astheprojectproceeds,anddeliverablesareaccumulated,onecandeterminetheactualcostandassessthecorrespondingearnedvalue.Exhibit7shows3samplesofsuchaprocess,attimes5,7,and9. Exhibit7–ComparisonofPlannedValue(SolidLine)WithSamplesofEarnedValues(Crosses)andActualCosts(Circles)a)InstantaneousValues b)CumulativeValues InExhibit7a,wehaveusedinstantaneousvalues,whileinExhibit7bwehaveplottedthesamedatausingcumulativevalues.OneofthecharacteristicsthatisimmediatelyobviousfromExhibit7isthatthecalculationismucheasiertoaccomplishusingtheinstantaneousvalues.Anumberoffeaturesoftheinstantaneousrepresentationmakeitmorepracticaltouse:thelinearityofthecurvesmakethedataeasiertoanalyze—itisalwayshardertoestimatequantitiesfromcurves;andthegreaterdeviationsoftheactualcostsandearnedvaluesonthelinearchartmakethemeasiertorecognizeandcompute. Oncewehavethevaluesfortheplannedcosts,actualcosts,andearnedvalues,itisstraightforwardtocomputethevaluesforCV(t)andSV(t)ateachofthepointsinExhibit7.Then,usingtheslopeoftheplannedvaluecurve,SPV,weuseequation(16)tocalculateα,andequation(19)tocalculateτ.Atthispoint,wehaveestimatesfortheeventualtotalcostover-runandthetotalscheduledelay. EstimatingCPI(t)andSPI(t) Exhibit8showstheestimatesforthevaluesofCPI(t)andSPI(t)correspondingtothesamepointsasinExhibit7.ThedottedlinesshowhowCPI(t)andSPI(t)changeovertime,evenwhentheover-runinbothcostandscheduleareinfactconstant.Onecanseethatbasedonthethreeestimatedvalues,itmightbehardtodecidewhattheoverallCPIandSPIfortheprojectmightbe.Theinherentcurvatureofthelineswouldmakeitdifficultpredictthefuturevaluesofthesequantities.OnlythroughtheknowledgeofthemodelpresentedheredoweunderstandthatthecurvesinCPI(t)andSPI(t)doinfactrepresentconstantvaluesfortheover-runinbothcostandschedule. LookingatExhibit8,oneseesthatthethreeestimatesforCPI(t)appeartoberising.Aninexperiencedprojectmanagermightinterpretthistomeanthatthingsareimproving.Infact,nothinghaschanged,andtheprojecthasanover-runinbothcostandschedule.The“apparent”slightimprovementintime3–9isduetothefactthatsomeactivitieswerenotcompletedduringthetime0–3.Thesehavenowbeencompletedandcreditisbeingearnedforthem.However,aconstantfractionofactivitiesareinfactdelayedineachtimeinterval,andCPI(t)willsoonleveloffasseeninExhibit6. Exhibit8–EstimationofCPI(t)andSPI(t) Ontheotherhand,SPI(t)risessteadily,eventuallyreaching1.0.However,asseeninExhibit6,SPI(t)willonlyreach1.0(denotingthecompletionofallactivities)afterthescheduledcompletiontime.Theprojectisrunninglate. Conclusions EVMprovidesprojectmanagerswithtriggersorearlywarningsignalsofprojecttrouble.Suchindicatorshavebeenfoundtobereliableasearlyas15%intoaproject.Betterplanningandresourceallocationassociatedwiththeearlyperiodsofaprojectmightbethecauseofthisreliability(Fleming&Koppelman,2000). However,thesewarningsignsaretime-dependent,andmustbeinterpretedwithgreatcare.Untilnow,therewasnowaytodeterminethistimedependence.TheextensionoftheWarburtonmodelprovidedhereestablishesthatthebehaviorofCPI(t)andSPI(t)overtimecanbecalculated.Laborcurvesintwodiverseindustries(constructionandsoftware)produceverysimilarcurvesforCPI(t)andSPI(t),leadingtothetentativeconclusionthatCPI(t)andSPI(t)arerelativelyindependentofthepreciseformoftheproject'slaborcurve.ThisagreeswithChristianandKallouris's(1991)observationthatmostprojectcurvesfollow“S”shapes.Thissuggeststhatthemodelhaswideapplicability. Exhibit8showsthatestimatesofCPI(t)earlyoninaprojectareinherentlyafunctionoftime.Aninexperiencedprojectmanagermightinterpretthistomeanthatwhiletheprojectdidnotstartwell,theriseinCPI(t)indicatesthatimprovementshavebeenmade.Infact,nothinghaschanged,andtheprojecthasanover-runinbothcostandschedule.Exhibit8alsoshowsthatSPI(t)isrisingsteadily,whichagainmightbeinterpretedasanimprovementintheproject'sprogress.Thisisnotso,astheprojectisrunninglate.Exhibit8showsthatinterpretingmeasuredvaluesforCPI(t)andSPI(t)istrickyunlessoneappreciatestheirinherenttime-dependentbehavior. TheWarburtonmodelrequirestwoconstants:thecostover-runrateandthetimedelaytorepairtherejectedactivities.Becausenotallactivitieswillbecompletedontime,aconstantfractionofthemareassumedtoberejectedandrequireextrawork.Byplottingtheinstantaneouslaborcurve,projectmanagersshouldbeabletoestimatetherequiredparametersearlyonintheproject,asthefirstfewactivitiesarecompleted. Morecomplexissuesneedtobeincludedinthemodelandaretopicsforfutureresearch.Themostinterestingissueisthatof“scopecreep,”whichincreasesthenumberofactivitiesandsoincreasesboththeactualcostandtheearnedvalue,whichinturnaffectsbothCPI(t)andSPI(t).Also,themodelassumesthatactivitiesareindependent,whichisclearlynottrue,asthecriticalpathdependsontheconnectionbetweenactivities.Thismightbeaddressedbyassumingthatthedelayinoneactivityresultsinthedelayofotheractivitiesfurtherdownthepath.Thisshouldmagnifytheeffectofthescheduledelayandwillpresumablymakethemodelmoresensitivetothescheduledelayparameter. Aprojectmanager'stoolkitshouldincludeamethodfordetermininghowparticularvaluesforCPI(t)andSPI(t),measuredatsomedefinitepointintime,canbeusedtoestimatetheeventualcostover-runandthescheduledelay.DespitethesimplicityoftheWarburtonmodel,anumberofinterestingfeaturesemerged.Whilemuchworkremainstobedone,itappearsthatthemodelisusefulandshowssomepromise. References Allen,W.(1979).Developingtheprojectplan.NotespreparedforEngineeringInstituteofCanadaAnnualCongressWorkshop,Toronto,pp.3-9. Anbari,F.T.(2003).Earnedvalueprojectmanagementmethodandextensions.ProjectManagementJournal,34(4),12. Anbari,F.T.(2002).Quantitativemethodsforprojectmanagement(2nded.).NewYork:InternationalInstituteforLearning. Anbari,F.T.(2001).Applicationsandextensionsoftheearnedvalueanalysismethod[CD-ROM].ProceedingsoftheProjectManagementInstitute2001Seminars&Symposium,November1-10,2001,Nashville,TN,USA.NewtownSquare,PA:ProjectManagementInstitute. Anbari,F.T.(1985).Asystemsapproachtoprojectevaluation.ProjectManagementJournal,16(3),21-26. Anbari,RT.(1980).Anoperatingmanagementcontrolsystemforlargescaleprojects.UnpublishedpaperpresentedatTheDecisionSciencesInstituteNinthAnnualMeeting,NortheastRegionalConference,Philadelphia,PA.SponsoredbytheNortheastDecisionSciencesInstitute. Christian,J.,&Kallouris,G.(1991).Anexpertsystemforpredictingthecost-timeprofilesofbuildingactivities.CanadianJournalofCivilEngineering,18,814. Cioffi,D.F.(2002).Managingprojectintegration.Vienna,VA:ManagementConcepts. Corovic,R.(2007).WhyEVMisnotgoodforscheduleperformanceanalyses(andhowitcouldbe…).TheMeasurableNews(Winter). Egan,Jr.,D.S.(1982).ThePerformanceIndex:Combiningcostandproductiondatatoshowhowgood(orbad)yourprojectreallyis!Proceedingsofthe7thInternetWorldCongressonPROJEKTPEAN,TheDanishProjectManagementSociety,355-364.Copenhagen,Denmark:TheDanishTechnicalPress. Fleming,Q.W.,&Koppelman,J.M.(2000).Earnedvalueprojectmanagement(2nded.).NewtownSquare,PA:ProjectManagementInstitute. Heinze,K.(1996).Costmanagementofcapitalprojects.NewYork:MarcelDekker,Inc. Henderson,K.(2004).Furtherdevelopmentsinearnedschedule.TheMeasurableNews,(Spring),15-22. Kerzner,H.(2006).Projectmanagement:Asystemsapproachtoplanning,scheduling,andcontrolling(9thed.).NewYork:JohnWiley&Sons. Kirn,E.H.(2000).Astudyontheeffectiveimplementationofearnedvaluemanagementmethodology,unpublisheddoctoraldissertation.TheGeorgeWashingtonUniversity,Washington,DC. Lewis,J.P.(2001).Projectplanning,scheduling,&control:Ahands-onguidetobringingprojectsinontimeandonbudget(3rded.).NewYork:McGraw-Hill. Lipke,W.(2003).Scheduleisdifferent.TheMeasurableNews(March),31–34. Lipke,W.(2004).Connectingearnedvaluetotheschedule.TheMeasurableNews(Winter),6–16. Lipke,W.,&Henderson,K.(2006).Earnedschedule–Aquantumadvance.APMYearbook. ProjectManagementInstitute(PMI).(2000).Aguidetotheprojectmanagementbodyofknowledge(2000ed.).NewtownSquare,PA:ProjectManagementInstitute. Putnam,L.H.(1978).Ageneralempiricalsolutiontothemacrosoftwaresizingandestimatingproblem.IEEETransactionsonSoftwareEngineering,SE-4(4),345-361. Singh,S.,&Lakanathan,G.(1992).Computer-basedcashflowmodel.Proceedingsofthe36thAnnualTransactionsoftheAmericanAssociationofCostEngineers,AACE,R.5.1-R.5.14. Vandevoorde,S.,&VanhouckeM.(2006).Acomparisonofdifferentprojectdurationforecastingmethodsusingearnedvaluemetrics.InternationalJournalofProjectManagement,24(4),289-302. Warburton,R.D.H.(1983).Managingandpredictingthecostsofreal-timesoftware.IEEETransactionsonSoftwareEngineering,SE-9(5),562-569. Warburton,R.D.H.(2008).Amacroearnedvaluemodel.AcceptedforthePMIResearchConference,Warsaw,Poland.Preprint. Webster,J.S.(2002).Meaningfulmetrics.PMNetwork,16(11),34-39. Wideman,M.(1994).Apragmaticapproachtousingresourceloading,productionandlearningcurvesonconstructionprojects.CanadianJournalofCivilEngineering,21,939-953. Wideman,M.(2001).Whatcanbelearnedofpracticalvalue?RetrievedNovember23,2007fromhttp://www.maxwideman.com/papers/resource/learned.htm Thismaterialhasbeenreproducedwiththepermissionofthecopyrightowner.Unauthorizedreproductionofthismaterialisstrictlyprohibited.Forpermissiontoreproducethismaterial,pleasecontactPMIoranylistedauthor. ©RogerD.H.Warburton,PhD,PMP&VijayKanabar,PhD,PMPOriginallypublishedaspartofPMIGlobalCongressProceedings2008-DenverColorado Advertisement Advertisement RelatedContent Article Innovation,Scheduling,Strategy,CostManagement,OrganizationalProjectManagement,Construction 1April2019 ProjectManagementJournal DeterminingContingenciesintheManagementofConstructionProjects ByOrtiz,JoséI.|Pellicer,Eugenio|Molenaar,KeithR. Thisresearchdescribesthemanagerialapproachesthatcontractorsfollowtodeterminedifferenttypesofcontingenciesinconstructionprojectmanagement.TwolargeSpanishgeneralcontractorswere… Article Agile,Scheduling,CostManagement,ScopeManagement 1September2018 PMNetwork SnapPrecision ByFewell,Jesse Ifyou'veworkedonagileprojects,you'velikelyheardanagilechampionmakebizarrestatementsaboutestimatingabudgetandschedule.Whenyoupressfurtherforestimates,youmightgetaneven… Article Scheduling,CostManagement,ScopeManagement 1December2017 PMNetwork MeasureOfRespect ByKhan,Zahid Arewemeasuringtherightkeyperformanceindicators(KPIs)?ProjectsuccessisusuallymeasuredbyKPIsrelatedtoscope,schedule,budgetandqualityrequirements. Article Scheduling,Complexity,CostManagement,ScopeManagement 1February2017 PMNetwork GamesPlan ByFisterGale,Sarah TheOlympicscapturetheworld'simagination.Buttheracebeginslongbeforeathletesarrive.CitiescompetetohosttheSummerandWinterGames,hopingtotakealeadroleontheglobalstage.But… Article RiskManagement,Scheduling,CostManagement,Construction 1February2017 PMNetwork OntheHorizon Amega-mosqueconstructionprojectisunderwayinAlgiers,Algeria—butitscompletiondateisn'tquiteclear.Atonepointscheduledtoopenthisyear,themosquewillbecomethethirdlargestin… Advertisement
延伸文章資訊
- 1Cost Performance Index (CPI) Explained with Examples
Cost Performance Index (CPI) can be calculated by dividing the earned value (EV) by the actual co...
- 2What is CPI - Cost Performance Index? - Ten Six Consulting
Cost Performance Index is a useful way of combining progress with budget to give a straightforwar...
- 3Understanding the Cost Performance Index (CPI) on Your ...
Cost performance index (CPI) also known as earned vs. burned, measures the financial effectivenes...
- 4Understanding Cost Performance Indexes | ProEst
The Cost Performance Index measures the earned value of a project against the actual cost incurre...
- 5What is Cost Performance Index? - Definition & Formula
Definition and Formula of Cost Performance Index ... Earned value is abbreviated as EV and actual...